West Midlands

North Warwickshire must find land for 1,154 more homes

North Warwickshire's brownfield register covers 37% of 5 years' need, so most of its new homes will have to come from land that is not on the register. It built 164% of the homes the Housing Delivery Test required.

North Warwickshire has to plan for 367 new homes a year, 1,835 over 5 years. Its brownfield register holds land for about 681 of them.

Brownfield with permission: 544 Other brownfield on the register: 137 Still to find: 1,154

Brownfield cover

37%

of 5 years' need, calculated. How

Still to find

1,154

homes over 5 years

Housing Delivery Test

164%

of required homes built, 2025 measurement

That is the 11th largest land gap of the 18 councils in West Midlands whose registers can be totalled.

How the housing target is worked out

The government's standard method starts from the homes North Warwickshire already has: 30,058, of which 0.8% is 240 a year. Homes there cost 7.77 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 52.6%, which gives 367 homes a year.

Delivery

Over the three years to March 2025, North Warwickshire delivered 831 homes against the 507 it was required to: 164%. No consequence applies.

What is on the brownfield register

31 live sites covering 19 hectares, of which 4 have no planning permission yet.

Nearby councils

2 of the 5 nearby councils with a cover figure have less brownfield cover than North Warwickshire.

CouncilHomes a yearBrownfield coversStill to find
Nuneaton and Bedworth760 47% 2,022
Tamworth437 23% 1,689
Hinckley and Bosworth667 12% 2,947
Coventry1,393 103% none
North West Leicestershire635 register incomplete —
Lichfield769 107% none

Councils with similar brownfield cover

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.

Housing Delivery Test 2025 measurement, published 17 August 2026.