How much land each council still has to find for new homes

London

Hammersmith and Fulham must find land for 8,324 more homes

Hammersmith and Fulham's brownfield register covers 38% of 5 years' need, so most of its new homes will have to come from land that is not on the register. It built only 91% of the homes the Housing Delivery Test required.

Hammersmith and Fulham has to plan for 2,702 new homes a year, 13,510 over 5 years. Its brownfield register holds land for about 5,188 of them.

Brownfield with permission: 2,494 Other brownfield on the register: 2,694 Still to find: 8,324

Brownfield cover

38%

of 5 years' need, calculated. How

Still to find

8,324

homes over 5 years

Housing Delivery Test

91%

of required homes built, 2025 measurement

That is the 5th largest land gap of the 14 councils in London whose registers can be totalled.

How the housing target is worked out

The government's standard method starts from the homes Hammersmith and Fulham already has: 99,527, of which 0.8% is 796 a year. Homes there cost 17.60 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 239.4%, which gives 2,702 homes a year.

Delivery

Over the three years to March 2025, Hammersmith and Fulham delivered 4,379 of the 4,798 it was required to: 91%. The government's published consequence: the council must publish an action plan.

What is on the brownfield register

23 live sites covering 24 hectares, of which 0 have no planning permission yet. 1 give no housing estimate, so the capacity above is a floor, not a total.

Nearby councils

1 of the 4 nearby councils with a cover figure has less brownfield cover than Hammersmith and Fulham.

CouncilHomes a yearBrownfield coversStill to find
Kensington and Chelsea4,525 42% 13,083
Wandsworth4,243 136% none
Westminster4,151 register incomplete —
Lambeth3,050 19% 12,311
Camden2,934 87% 1,874
Brent3,047 register incomplete —

Councils with similar brownfield cover

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.

Housing Delivery Test 2025 measurement, published 17 August 2026.