Skip to content
Land·Gap

How much land each council still has to find for new homes

East of England

Dacorum must find land for 4,326 more homes

Dacorum's brownfield register covers 38% of 5 years' need, so most of its new homes will have to come from land that is not on the register. It built only 52% of the homes the Housing Delivery Test required.

Dacorum has to plan for 1,401 new homes a year, 7,005 over 5 years. Its brownfield register holds land for about 2,678 of them.

Brownfield with permission: 1,038 Other brownfield on the register: 1,640 Still to find: 4,326

Brownfield cover

38%

of 5 years' need, calculated. How

Still to find

4,326

homes over 5 years

Housing Delivery Test

52%

of required homes built, 2025 measurement

That is the 4th largest land gap of the 20 councils in East of England whose registers can be totalled.

How the housing target is worked out

The government's standard method starts from the homes Dacorum already has: 68,352, of which 0.8% is 547 a year. Homes there cost 13.22 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 156.2%, which gives 1,401 homes a year.

Delivery

Over the three years to March 2025, Dacorum delivered 1,578 of the 3,051 it was required to: 52%. The government's published consequence: the presumption in favour of sustainable development applies.

What is on the brownfield register

35 live sites covering 62 hectares, of which 21 have no planning permission yet.

Nearby councils

2 of the 3 nearby councils with a cover figure have less brownfield cover than Dacorum.

CouncilHomes a yearBrownfield coversStill to find
St Albans1,653 8% 7,640
Watford817 register incomplete —
Three Rivers752 34% 2,497
Luton1,128 register incomplete —
Hertsmere975 register incomplete —
Welwyn Hatfield821 110% none

Councils with similar brownfield cover

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.

Housing Delivery Test 2025 measurement, published 17 August 2026.