Skip to content
Land·Gap

How much land each council still has to find for new homes

North East

County Durham must find land for 6,489 more homes

County Durham's brownfield register covers 36% of 5 years' need, so most of its new homes will have to come from land that is not on the register. It built 131% of the homes the Housing Delivery Test required.

County Durham has to plan for 2,035 new homes a year, 10,175 over 5 years. Its brownfield register holds land for about 3,686 of them.

Brownfield with permission: 2,266 Other brownfield on the register: 1,420 Still to find: 6,489

Brownfield cover

36%

of 5 years' need, calculated. How

Still to find

6,489

homes over 5 years

Housing Delivery Test

131%

of required homes built, 2025 measurement

That is the largest land gap of the 8 councils in North East whose registers can be totalled.

How the housing target is worked out

The government's standard method starts from the homes County Durham already has: 254,383, of which 0.8% is 2,035 a year. Homes there cost 4.60 times local workplace earnings, on the five-year average. That is at or below 5, so there is no affordability uplift and the target stays at 2,035 homes a year.

Delivery

Over the three years to March 2025, County Durham delivered 4,609 homes against the 3,529 it was required to: 131%. No consequence applies.

What is on the brownfield register

69 live sites covering 160 hectares, of which 35 have no planning permission yet. 7 give no housing estimate, so the capacity above is a floor, not a total.

Nearby councils

None of the 4 nearby councils with a cover figure have less brownfield cover than County Durham.

CouncilHomes a yearBrownfield coversStill to find
Sunderland1,072 74% 1,369
Darlington453 register incomplete —
Gateshead796 160% none
Newcastle upon Tyne1,245 register incomplete —
Hartlepool370 104% none
Stockton-on-Tees778 56% 1,692

Councils with similar brownfield cover

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.

Housing Delivery Test 2025 measurement, published 17 August 2026.