South East
Oxford's brownfield register covers five years of its target
Oxford's brownfield register holds more than 5 years' need, 106% of it, on the council's own capacity estimates. It built only 65% of the homes the Housing Delivery Test required.
Oxford has to plan for 1,079 new homes a year, 5,395 over 5 years. Its brownfield register holds land for about 5,691 of them.
Homes to spare
298
homes over 5 years
Housing Delivery Test
65%
of required homes built, 2025 measurement
Oxford is one of the councils in South East with no land gap on this measure; 33 councils there have registers that can be totalled.
How the housing target is worked out
The government's standard method starts from the homes Oxford already has: 60,527, of which 0.8% is 484 a year. Homes there cost 11.46 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 122.7%, which gives 1,079 homes a year.
Delivery
Over the three years to March 2025, Oxford delivered 1,099 of the 1,701 it was required to: 65%. The government's published consequence: the presumption in favour of sustainable development applies.
What is on the brownfield register
88 live sites covering 279 hectares, of which 59 have no planning permission yet. 14 give no housing estimate, so the capacity above is a floor, not a total.
Nearby councils
4 of the 5 nearby councils with a cover figure have less brownfield cover than Oxford.
| Council | Homes a year | Brownfield covers | Still to find |
|---|---|---|---|
| Vale of White Horse | 970 | 38% | 3,029 |
| Cherwell | 1,131 | register incomplete | — |
| South Oxfordshire | 1,208 | 78% | 1,319 |
| West Oxfordshire | 901 | 12% | 3,977 |
| Buckinghamshire | 4,344 | 14% | 18,662 |
| Reading | 987 | 334% | none |
Councils with similar brownfield cover
- Oldham: 106% cover
- Lichfield: 107% cover
- Hartlepool: 104% cover
- Coventry: 103% cover
- Worcester: 109% cover
- Welwyn Hatfield: 110% cover
A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.
Housing Delivery Test 2025 measurement, published 17 August 2026.