Buckinghamshire must find land for 18,662 more homes

Buckinghamshire is among the councils furthest from meeting its housing target on brownfield land: its register covers 14% of 5 years' need. It built only 94% of the homes the Housing Delivery Test required.

Buckinghamshire has to plan for 4,344 new homes a year, 21,720 over 5 years. Its brownfield register holds land for about 3,060 of them.

Brownfield with permission: 2,183 Other brownfield on the register: 877 Still to find: 18,662

Brownfield cover

14%

of 5 years' need, calculated. How

Still to find

18,662

homes over 5 years

Housing Delivery Test

94%

of required homes built, 2025 measurement

That is the largest land gap of the 33 councils in South East whose registers can be totalled.

How the housing target is worked out

The government's standard method starts from the homes Buckinghamshire already has: 240,719, of which 0.8% is 1,926 a year. Homes there cost 11.61 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 125.6%, which gives 4,344 homes a year.

Delivery

Over the three years to March 2025, Buckinghamshire delivered 7,763 of the 8,274 it was required to: 94%. The government's published consequence: the council must publish an action plan.

What is on the brownfield register

200 live sites covering 220 hectares, of which 25 have no planning permission yet. 36 give no housing estimate, so the capacity above is a floor, not a total.

Nearby councils

None of the 3 nearby councils with a cover figure have less brownfield cover than Buckinghamshire.

CouncilHomes a yearBrownfield coversStill to find
Windsor and Maidenhead1,407 register incomplete —
Slough824 register incomplete —
Three Rivers752 34% 2,497
Dacorum1,401 38% 4,326
South Oxfordshire1,208 78% 1,319
Watford817 register incomplete —

Councils with similar brownfield cover

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.

Housing Delivery Test 2025 measurement, published 17 August 2026.