North East

North Tyneside must plan for 982 homes a year

North Tyneside has to plan for 982 homes a year, the 5th highest target of the 12 councils in North East. It built only 65% of the homes the Housing Delivery Test required.

That is 4,910 homes over 5 years.

No brownfield cover figure for North Tyneside. Only 73% of the sites on this council's brownfield register give a housing estimate, so its capacity cannot be totalled. We publish the cover figure only where at least 80% do.

That is a gap in the register, not evidence that North Tyneside has no brownfield land.

How the housing target is worked out

The government's standard method starts from the homes North Tyneside already has: 102,122, of which 0.8% is 817 a year. Homes there cost 6.06 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 20.1%, which gives 982 homes a year.

Delivery

Over the three years to March 2025, North Tyneside delivered 1,504 of the 2,306 it was required to: 65%. The government's published consequence: the presumption in favour of sustainable development applies.

What is on the brownfield register

109 live sites covering 126 hectares, of which 71 have no planning permission yet. 29 of them give no housing estimate.

Nearby councils

CouncilHomes a yearBrownfield coversStill to find
South Tyneside626 register incomplete —
Newcastle upon Tyne1,245 register incomplete —
Gateshead796 160% none
Sunderland1,072 74% 1,369
Northumberland1,676 54% 3,840
County Durham2,035 36% 6,489

Councils with a similar housing target

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.

Housing Delivery Test 2025 measurement, published 17 August 2026.