Dartford's brownfield register covers five years of its target

Dartford's brownfield register holds more than 5 years' need, 164% of it, on the council's own capacity estimates. It built 96% of the homes the Housing Delivery Test required, just short of the full number.

Dartford has to plan for 756 new homes a year, 3,780 over 5 years. Its brownfield register holds land for about 6,187 of them.

Brownfield with permission: 4,158 Other brownfield on the register: 2,029 Covers 5 years of need, with 2,409 homes to spare

Brownfield cover

164%

of 5 years' need, calculated. How

Homes to spare

2,409

homes over 5 years

Housing Delivery Test

96%

of required homes built, 2025 measurement

Dartford is one of the councils in South East with no land gap on this measure; 33 councils there have registers that can be totalled.

How the housing target is worked out

The government's standard method starts from the homes Dartford already has: 50,653, of which 0.8% is 405 a year. Homes there cost 9.55 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 86.5%, which gives 756 homes a year.

Delivery

Over the three years to March 2025, Dartford delivered 2,226 of the 2,330 it was required to: 96%. No consequence applies.

What is on the brownfield register

60 live sites covering 309 hectares, of which 41 have no planning permission yet. 2 give no housing estimate, so the capacity above is a floor, not a total.

Nearby councils

None of the 1 nearby councils with a cover figure have less brownfield cover than Dartford.

CouncilHomes a yearBrownfield coversStill to find
Bexley1,898 register incomplete —
Thurrock1,079 register incomplete —
Gravesham687 register incomplete —
Greenwich2,492 168% none
Barking and Dagenham1,338 register incomplete —
Havering1,947 register incomplete —

Councils with similar brownfield cover

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.

Housing Delivery Test 2025 measurement, published 17 August 2026.