How much land each council still has to find for new homes

North West

Cheshire East must plan for 2,530 homes a year

Cheshire East has to plan for 2,530 homes a year, the 2nd highest target of the 35 councils in North West. It built 213% of the homes the Housing Delivery Test required.

That is 12,650 homes over 5 years.

No brownfield cover figure for Cheshire East. Only 51% of the sites on this council's brownfield register give a housing estimate, so its capacity cannot be totalled. We publish the cover figure only where at least 80% do.

That is a gap in the register, not evidence that Cheshire East has no brownfield land.

How the housing target is worked out

The government's standard method starts from the homes Cheshire East already has: 192,819, of which 0.8% is 1,543 a year. Homes there cost 8.37 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 64.0%, which gives 2,530 homes a year.

Delivery

Over the three years to March 2025, Cheshire East delivered 6,508 homes against the 3,061 it was required to: 213%. No consequence applies.

What is on the brownfield register

61 live sites covering 90 hectares, of which 1 have no planning permission yet. 30 of them give no housing estimate.

Nearby councils

CouncilHomes a yearBrownfield coversStill to find
Stockport1,901 42% 5,488
Trafford1,621 register incomplete —
High Peak580 43% 1,655
Staffordshire Moorlands501 register incomplete —
Manchester2,601 register incomplete —
Salford1,396 612% none

Councils with a similar housing target

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.

Housing Delivery Test 2025 measurement, published 17 August 2026.