Brighton and Hove must find land for 4,168 more homes

Brighton and Hove's brownfield register covers 67% of 5 years' need, so most of its new homes will have to come from land that is not on the register. It built only 50% of the homes the Housing Delivery Test required.

Brighton and Hove has to plan for 2,490 new homes a year, 12,450 over 5 years. Its brownfield register holds land for about 8,284 of them.

Brownfield with permission: 3,510 Other brownfield on the register: 4,774 Still to find: 4,168

Brownfield cover

67%

of 5 years' need, calculated. How

Still to find

4,168

homes over 5 years

Housing Delivery Test

50%

of required homes built, 2025 measurement

That is the 7th largest land gap of the 33 councils in South East whose registers can be totalled.

How the housing target is worked out

The government's standard method starts from the homes Brighton and Hove already has: 135,486, of which 0.8% is 1,084 a year. Homes there cost 11.83 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 129.8%, which gives 2,490 homes a year.

Delivery

Over the three years to March 2025, Brighton and Hove delivered 3,480 of the 6,980 it was required to: 50%. The government's published consequence: the presumption in favour of sustainable development applies.

What is on the brownfield register

202 live sites covering 81 hectares, of which 116 have no planning permission yet. 29 give no housing estimate, so the capacity above is a floor, not a total.

Nearby councils

2 of the 3 nearby councils with a cover figure have less brownfield cover than Brighton and Hove.

CouncilHomes a yearBrownfield coversStill to find
Adur535 70% 815
Lewes855 24% 3,240
Worthing855 register incomplete —
Mid Sussex1,343 21% 5,316
Horsham1,329 register incomplete —
Arun1,470 register incomplete —

Councils with similar brownfield cover

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.