Sutton must plan for 1,651 homes a year
Sutton has to plan for 1,651 homes a year, the 30th highest target of the 33 councils in London. It built only 81% of the homes the Housing Delivery Test required.
That is 8,255 homes over 5 years.
No brownfield cover figure for Sutton. Only 53% of the sites on this council's brownfield register give a housing estimate, so its capacity cannot be totalled. We publish the cover figure only where at least 80% do.
That is a gap in the register, not evidence that Sutton has no brownfield land.
How the housing target is worked out
The government's standard method starts from the homes Sutton already has: 86,957, of which 0.8% is 696 a year. Homes there cost 12.23 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 137.4%, which gives 1,651 homes a year.
Delivery
Over the three years to March 2025, Sutton delivered 1,145 of the 1,407 it was required to: 81%. The government's published consequence: the council must add a buffer to its land supply.
What is on the brownfield register
103 live sites covering 48 hectares, of which 55 have no planning permission yet. 48 of them give no housing estimate.
Nearby councils
| Council | Homes a year | Brownfield covers | Still to find |
|---|---|---|---|
| Merton | 2,050 | register incomplete | — |
| Epsom and Ewell | 834 | 20% | 3,329 |
| Croydon | 2,843 | 130% | none |
| Kingston upon Thames | 1,551 | register incomplete | — |
| Wandsworth | 4,243 | 136% | none |
| Lambeth | 3,050 | 19% | 12,311 |
Councils with a similar housing target
- St Albans: 1,653 homes a year
- East Suffolk: 1,658 homes a year
- Medway: 1,666 homes a year
- Leicester: 1,631 homes a year
- Wirral: 1,630 homes a year
- Northumberland: 1,676 homes a year
A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.
Housing Delivery Test 2025 measurement, published 17 August 2026.