London
Croydon's brownfield register covers five years of its target
Croydon's brownfield register holds more than 5 years' need, 130% of it, on the council's own capacity estimates. It built 105% of the homes the Housing Delivery Test required.
Croydon has to plan for 2,843 new homes a year, 14,215 over 5 years. Its brownfield register holds land for about 18,418 of them.
Homes to spare
4,204
homes over 5 years
Housing Delivery Test
105%
of required homes built, 2025 measurement
Croydon is one of the councils in London with no land gap on this measure; 14 councils there have registers that can be totalled.
How the housing target is worked out
The government's standard method starts from the homes Croydon already has: 170,279, of which 0.8% is 1,362 a year. Homes there cost 10.72 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 108.7%, which gives 2,843 homes a year.
Delivery
Over the three years to March 2025, Croydon delivered 6,131 homes against the 5,842 it was required to: 105%. No consequence applies.
What is on the brownfield register
489 live sites covering 172 hectares, of which 152 have no planning permission yet. 1 give no housing estimate, so the capacity above is a floor, not a total.
Nearby councils
1 of the 3 nearby councils with a cover figure has less brownfield cover than Croydon.
| Council | Homes a year | Brownfield covers | Still to find |
|---|---|---|---|
| Sutton | 1,651 | register incomplete | — |
| Merton | 2,050 | register incomplete | — |
| Bromley | 2,880 | register incomplete | — |
| Lambeth | 3,050 | 19% | 12,311 |
| Lewisham | 2,547 | 213% | none |
| Wandsworth | 4,243 | 136% | none |
Councils with similar brownfield cover
- Bracknell Forest: 130% cover
- Surrey Heath: 134% cover
- Wirral: 134% cover
- Derbyshire Dales: 123% cover
- Peterborough: 137% cover
- Waltham Forest: 139% cover
A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.