East of England

North Hertfordshire must find land for 3,894 more homes

North Hertfordshire has to plan for 1,036 new homes a year, 5,180 over 5 years. Its brownfield register holds land for about 1,285 of them.

Brownfield with permission: 572 Other brownfield on the register: 713 Still to find: 3,894

Brownfield cover

25%

of 5 years' need, calculated. How

Still to find

3,894

homes over 5 years

Housing Delivery Test

75%

of required homes built, 2025 measurement

Delivery

Over the three years to March 2025, North Hertfordshire delivered 1,424 of the 1,910 homes it was required to: 75%. The government's published consequence: the council must add a 20% buffer to its land supply.

What is on the brownfield register

57 live sites covering 40 hectares, of which 12 have no planning permission yet. 8 give no housing estimate, so the capacity above is a floor, not a total.

A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.

Housing Delivery Test 2025 measurement, published 17 August 2026.