Tunbridge Wells must find land for 2,998 more homes
Tunbridge Wells's brownfield register covers 45% of 5 years' need, so most of its new homes will have to come from land that is not on the register. It built only 93% of the homes the Housing Delivery Test required.
Tunbridge Wells has to plan for 1,100 new homes a year, 5,500 over 5 years. Its brownfield register holds land for about 2,502 of them.
Still to find
2,998
homes over 5 years
Housing Delivery Test
93%
of required homes built, 2025 measurement
That is the 15th largest land gap of the 33 councils in South East whose registers can be totalled.
How the housing target is worked out
The government's standard method starts from the homes Tunbridge Wells already has: 53,316, of which 0.8% is 427 a year. Homes there cost 13.31 times local workplace earnings, on the five-year average. Every 1% that ratio sits above 5 adds 0.95% to the baseline, an uplift of 157.9%, which gives 1,100 homes a year.
Delivery
Over the three years to March 2025, Tunbridge Wells delivered 1,863 of the 1,999 it was required to: 93%. The government's published consequence: the council must publish an action plan.
What is on the brownfield register
125 live sites covering 52 hectares, of which 5 have no planning permission yet.
Nearby councils
2 of the 4 nearby councils with a cover figure have less brownfield cover than Tunbridge Wells.
| Council | Homes a year | Brownfield covers | Still to find |
|---|---|---|---|
| Tonbridge and Malling | 1,117 | register incomplete | — |
| Wealden | 1,465 | register incomplete | — |
| Sevenoaks | 1,166 | 81% | 1,110 |
| Maidstone | 1,373 | 58% | 2,849 |
| Tandridge | 819 | 42% | 2,372 |
| Rother | 895 | 16% | 3,757 |
Councils with similar brownfield cover
- Thanet: 45% cover
- Rushmoor: 46% cover
- Lincoln: 47% cover
- Nuneaton and Bedworth: 47% cover
- High Peak: 43% cover
- Stockport: 42% cover
A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.
Housing Delivery Test 2025 measurement, published 17 August 2026.