South East
Havant must plan for 884 homes a year
Havant has to plan for 884 new homes a year, 4,420 over 5 years.
No brownfield cover figure for Havant. Only 77% of the sites on this council's brownfield register give a housing estimate, so its capacity cannot be totalled. We publish the cover figure only where at least 80% do.
That is a gap in the register, not evidence that Havant has no brownfield land.
Delivery
Over the three years to March 2025, Havant delivered 1,228 of the 1,538 homes it was required to: 80%. The government's published consequence: the council must add a 20% buffer to its land supply.
What is on the brownfield register
75 live sites covering 144 hectares, of which 33 have no planning permission yet. 17 of them give no housing estimate.
A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.
Housing Delivery Test 2025 measurement, published 17 August 2026.