Knowsley's brownfield register covers five years of its target
Knowsley has to plan for 631 new homes a year, 3,155 over 5 years. Its brownfield register holds land for about 6,705 of them.
Homes to spare
3,549
homes over 5 years
Housing Delivery Test
245%
of required homes built, 2025 measurement
Delivery
Over the three years to March 2025, Knowsley delivered 1,888 of the 772 homes it was required to: 245%. The government's published consequence: no consequence.
What is on the brownfield register
121 live sites covering 275 hectares, of which 64 have no planning permission yet. 20 give no housing estimate, so the capacity above is a floor, not a total.
A council short of land has to find more, and the 17 August 2026 planning framework widened what counts as grey belt. This page describes the council's position. It does not say whether any particular piece of land would get permission.
Housing Delivery Test 2025 measurement, published 17 August 2026.